process Planning and zoning 11 min read

Getting a DA in Queensland, step-by-step

How to get a development approval in QLD: MCU, IDAS stages, SARA referrals, building approval under Building Act 1975, private certifier hold points.

Ask Chalkline about this →

TL;DR

Queensland splits approvals into two separate instruments: a Development Approval (DA) under the Planning Act 2016 and a Building Approval (BA) under the Building Act 1975. Most new detached houses in low-density zones are accepted development for planning purposes (no DA needed), but a BA from a licensed building certifier is always required. Where a DA is needed (overlays, higher-density zones, intensified land use), the statutory decision timeframe is 35 business days for the assessment stage, but real-world council turnaround on code assessable residential work typically runs 45 to 70+ business days. If SARA (the state referral agency) is triggered by a state-controlled road, heritage, vegetation clearing or coastal management overlay, add 25 business days for the referral stage. Engage a building certifier early: the five mandatory inspection hold points (excavation, footings, slab, frame, final) are concrete pour gates and missing one stops the job. The Queensland Home Warranty Scheme (QHWS) is compulsory for residential building work over $3,300 ex-GST; the contractor pays the premium before works start.

When you do this

Queensland residential construction runs under two parallel approval tracks:

TrackLegislationIssuing bodyWhen required
Development Approval (DA)Planning Act 2016 (Qld)Local council (or SARA for state work)Assessable development: MCU, overlays, reconfiguring a lot
Building Approval (BA)Building Act 1975 (Qld)Licensed building certifier (private or council)All Class 1a buildings, always required

Accepted development (no DA required): Under Planning Regulation 2017 (Qld) Schedule 6, a new detached house in a standard low-density residential zone is typically accepted development. No planning approval is needed; self-assess against the planning scheme codes and go straight to a BA. (verified 2026-05-09, Queensland Legislation)

Assessable development (DA required): A DA is required when the proposal is code assessable or impact assessable under the local planning scheme. Common residential triggers:

TriggerAssessment typeNotes
MCU in a non-standard zoneCode or impact assessableMCU = starting a new use or intensifying an existing one (Planning Act 2016 Qld Sch 2)
Heritage place overlayCode assessableState and local heritage places
Bushfire management areaCode or impact assessableVaries by planning scheme and lot
Coastal management or erosion-prone areaCode assessableTriggers SARA referral
High or medium density residential zoneMay require DA from Dec 2025Local governments can now opt in (Planning Amendment Regulation 2025, effective 3 December 2025)
Flood hazard areaCode or impact assessableCheck local mapping
Reconfiguring a lotCode assessableSubdivision, boundary realignment
Dual occupancy, secondary dwellingVaries by councilCheck planning scheme assessment tables

Code assessable applications are assessed against specific codes only, with a presumption of approval if benchmarks are met. Impact assessable applications are assessed against the whole scheme and publicly notified; submitters get third-party appeal rights.

Who’s involved

PartyRole
Owner / developerSigns the application, holds the development approval once issued
BuilderOften briefs the BA; holds the QBCC licence for construction
Town plannerPrepares and lodges the DA, manages the SARA referral and information request process
Local council (assessment manager)Assesses DA for most residential work, issues development approval
SARA (State Assessment and Referral Agency)State-level referral or assessment for development affecting state interests (transport corridors, heritage, vegetation, coastal)
Private building certifierAssesses and issues the BA, conducts mandatory stage inspections
QBCCLicences builders and certifiers, administers Queensland Home Warranty Scheme, investigates complaints
Referral agenciesConcurrence agencies (can impose conditions) or advice agencies: Transport and Main Roads, Department of Environment and Heritage, local fire authority, etc.

Steps

Track A: Development Approval (where required)

  1. Determine whether a DA is required. Check the local planning scheme assessment tables. Most new detached houses on standard residential lots are accepted development; skip to Track B. If the site has an overlay or is in a higher-density zone, a DA is likely needed.

  2. Pre-application consultation (optional). Council and SARA both offer pre-lodgement advice. Use it to confirm whether SARA will be triggered before the formal clock starts.

  3. Prepare the application. A properly made DA requires the IDAS (Integrated Development Assessment System) forms, site plans, and any specialist reports the overlays require (bushfire, hydraulic, ecological, heritage).

  4. Lodge the application (Part 1). Lodge online via the MyDAS2 portal or directly with council. The application must be properly made before the clock starts. Council has 10 business days to issue a confirmation notice. (verified 2026-05-09, Consult Planning)

  5. Referral stage (Part 2, where triggered). If SARA or another referral agency is triggered under Schedules 9 and 10 of the Planning Regulation 2017, the assessment manager forwards the application. Referral agencies have 25 business days after referral confirmation. Concurrence agencies can impose conditions or recommend refusal; advice agencies advise only. (verified 2026-05-09, Consult Planning)

  6. Information request (Part 3, where issued). Council may issue an information request within 10 business days of Part 1 ending. The applicant has 3 months to respond before the application lapses; the clock pauses while the request is outstanding. (verified 2026-05-09, Consult Planning)

  7. Public notification (Part 4, impact assessable only). Minimum 15 business days. Code assessable applications are not notified. (verified 2026-05-09, Consult Planning)

  8. Decision (Part 5). Council has 35 business days to decide (less up to 10 days for any information request time). Notification of the decision within 5 business days. Real-world: code assessable residential DAs typically run 45 to 70+ business days total; impact assessable with submissions run longer. (verified 2026-05-09, Consult Planning)

  9. Currency period. A material change of use approval has a 6-year currency period to commence the use. (verified 2026-05-09, Queensland Government)

Track B: Building Approval (always required)

  1. Engage a licensed building certifier. The builder typically engages a private certifier on the owner’s behalf. All certifiers must be QBCC-licensed. Class A private certifiers can issue a BA that also constitutes a development approval (planning assessment included) for building work on accepted development sites. Class B certifiers do not hold this endorsement. Council can act as certifier where no private certifier is engaged. (verified 2026-05-09, Building Act 1975 Qld)

  2. Lodge plans and pay fees. Submit architectural and engineering documentation. The certifier assesses NCC/BCA, Queensland Development Code (QDC), and Building Act 1975 compliance. Brisbane City Council charges $75.20 to lodge building certification documents online. (verified 2026-05-09, Brisbane City Council)

  3. QHWS insurance before work starts. For residential building work over $3,300 (inc. GST), the builder must have a Queensland Home Warranty Scheme (QHWS) policy in place before commencing. The contractor pays the premium based on the insurable value. Maximum cover is $200,000; structural defects covered for 6 years 6 months, non-structural for 6 months. (verified 2026-05-09, QBCC)

  4. Certifier issues the BA. Building approvals for Class 1a residential work are valid for 18 months. (verified 2026-05-09, QBCC)

  5. Five mandatory hold points. Under Building Regulation 2021 (Qld), a Class 1a detached house has five mandatory inspection stages. Concrete cannot be poured until the certifier has inspected and signed off. (verified 2026-05-09, QBCC)

    StageWhenWhat is checked
    ExcavationAfter excavation, before any concreteFoundation material, setout
    FootingsAfter formwork and reo placedBefore footing concrete pour
    SlabAfter formwork and reo placedBefore slab concrete pour
    FrameAfter frame erectedBefore internal linings fixed
    FinalAll work completeDrainage, termite, weatherproofing, wet area membranes, glazing, smoke alarms, energy efficiency
  6. Certificate of classification. On final inspection sign-off, the certifier issues a certificate of classification (Class 1a). This is the QLD equivalent of an occupation certificate. The certifier notifies local government. The owner can then legally occupy.

Documents needed

DocumentTrackNotes
IDAS formsDAForm set depends on development type; lodged via MyDAS2
Site analysis planDALot dimensions, easements, overlays
Architectural and engineering drawingsBothSite, floor, elevation, section, structural details
Overlay assessment reportDATown planner; demonstrates compliance with applicable code
Bushfire management planDA (bushfire overlay)Accredited bushfire consultant
Hydraulic / flood assessmentDA (flood overlay)Hydraulic engineer
Heritage impact assessmentDA (heritage overlay)State or local heritage trigger
Ecological assessmentDA (vegetation clearing)Ecologist
NCC / QDC compliance documentationBACertifier or building designer
Energy efficiency documentationBANCC Section J / climate zone compliance
QHWS insurance certificateBABuilder (via QBCC); required before work starts

Common holds

HoldCauseFix
Application not properly madeMissing IDAS form, incomplete plans, incorrect feeCheck the DA checklist with council before lodging
SARA referral delayState interest triggered (transport corridor, heritage, vegetation clearing, coastal)Engage a town planner with SARA experience; consider pre-lodgement SARA consultation
Information requestInsufficient overlay assessment, missing specialist reportFront-load specialist reports; get pre-application feedback from council
Impact assessable submissionThird-party objection to public notificationIdentify likely objectors early; consider design changes that address the concern
Wrong assessment pathwayApplied as code assessable when impact assessable was required, or vice versaCheck the planning scheme assessment tables; get a planning advice letter before lodging
Certifier not bookedBuilder failed to engage certifier before excavation; concrete poured before inspectionEngage the certifier at contract signing, not when the excavator turns up
Inspection failureNon-compliance at a mandatory hold point (wrong reo, incorrect setout, non-conforming frame)Stop works, notify certifier, rectify before concrete poured or linings fixed
QHWS not in placeWork commenced without warranty insuranceQBCC can issue stop-work notices; builder is liable for unlicensed building work
Currency lapseDA not acted on within the 6-year currency periodSeek an extension or re-lodge; conditions of the original approval may have changed

References

  • Planning Act 2016 (Qld), legislation.qld.gov.au (verified 2026-05-09). Primary planning statute; development categories, assessment requirements, DA rules framework.
  • Planning Regulation 2017 (Qld), legislation.qld.gov.au (verified 2026-05-09). Schedules 8, 9 and 10 (SARA and referral agency triggers); Schedule 6 (accepted development for dwelling houses).
  • Building Act 1975 (Qld), legislation.qld.gov.au (verified 2026-05-09). Building approvals, private certifier classes, building development applications.
  • Building Regulation 2021 (Qld), legislation.qld.gov.au (verified 2026-05-09). Mandatory inspection stages for Class 1a buildings (s.44).
  • Development assessment process, planning.qld.gov.au (verified 2026-05-09). Five-stage DA process overview under DA Rules v3.0 (effective 18 July 2025).
  • State Assessment and Referral Agency (SARA), planning.qld.gov.au (verified 2026-05-09). SARA roles, FastTrack5 pathway, pre-lodgement advice.
  • Building inspections and approvals, QBCC (verified 2026-05-09). Mandatory inspection stages for Class 1a residential buildings.
  • Queensland Home Warranty Scheme, QBCC (verified 2026-05-09). Threshold ($3,300 inc GST), coverage ($200,000), duration (6 years 6 months structural).
  • Building a new house, Brisbane City Council (verified 2026-05-09). Accepted development criteria, overlay triggers, building certification lodgement fee.
  • DA process timeframes, Consult Planning (verified 2026-05-09). DA Rules statutory timeframes by part: confirmation (10 bd), referral (25 bd), info request (10 bd / 3 months response), public notification (15 bd), decision (35 bd).

See also


Last updated: 2026-05-09. Verified: 2026-05-09. Quarterly review for currency.