process Practical and on-site 10 min read

Residential paving: pavers, concrete, sub-base and drainage

Australian residential paving: sub-base depths, bedding sand, edge restraints, falls, drainage compliance and council approvals. AS 3727.1:2016 explained.

Ask Chalkline about this →

TL;DR

Residential paving is governed by AS 3727.1:2016 (verified 2026-05-08) and NCC 2022 Housing Provisions Part 3.3 for drainage. Sub-base depth is the most under-specified part of residential paving jobs: 100 mm compacted roadbase for driveways, 75 mm for pedestrian areas. Bedding sand sits at 30 mm (uncompacted) over the sub-base. Falls away from the building are mandatory: minimum 1:40 (25 mm per metre) on impermeable surfaces within 1 m of a structure per NCC 2022 Part 3.3 (verified 2026-05-08). Pavers cost $75 to $160/m2 installed; poured concrete $100 to $160/m2 installed (2026). Crossovers across council verge require a permit in every state. The most common defect on residential paving jobs is settling caused by inadequate sub-base compaction or uncontrolled water ingress under the base.

When you do this

Residential paving is typically sequenced after:

  • External drainage and stormwater lines are in (paving over drainage is a coring problem later)
  • Slab or footing finished and cured (slab edge sets the floor level the paving must drain away from)
  • External works like retaining walls, garden edging and fencing are complete or staged so you are not wheeling equipment past finished paving

For new dwellings, paving follows the “lock-up” stage. For renovations and landscaping jobs, paving can be standalone.

Who’s involved

RoleResponsibility
Builder or landscaperProject management, base prep supervision, final level and fall check
Paving contractorSub-base and bedding prep, paver laying, jointing, edge restraints
ConcreterPoured concrete option (slab finish, driveway crossover)
Hydraulic plumberPits, grates, drains connected to stormwater
CouncilDriveway crossover permit (road reserve / verge section)

Steps

1. Design and council approval

Check council requirements before ordering materials:

  • Driveway crossover (verge): The section crossing council land between the property boundary and road pavement requires a permit in every state. Lodge with council before work starts. Typical turnaround 2 to 6 weeks. Fees vary: bond/security deposit often required (refundable if no damage to public assets).
  • NSW exempt development: Driveways, hardstands, paths and paved areas are exempt development if stormwater runoff connects to the existing stormwater drainage system and work meets AS/NZS 2890.1:2004. Total impervious area must not impede overland flow or concentrate runoff onto neighbouring properties (State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, verified 2026-05-08). Check your LEP for any site coverage cap; many councils apply a 60% hard surface limit on residential lots.
  • Overland flow paths: Paving must not block or redirect natural overland flow. Council DCP and state stormwater codes apply. In flood-prone areas, check the LEP/DCP flood overlay before designing any fill or impermeable surface.
  • Permeable paving: Interlocking permeable concrete pavers may satisfy council stormwater requirements without a formal drainage connection. Check with council before designing permeable systems as the sole stormwater treatment. CMAA PE01 manual covers design.

2. Set out levels

  • Establish the finished floor level (FFL) of the slab, step or door threshold. Paving must fall away, not towards, the structure.
  • NCC 2022 Part 3.3 minimum fall requirement: 25 mm per metre (1:40) over the first 1 m from the building on reasonably impermeable surfaces (concrete or clay paving) in low rainfall intensity areas (verified 2026-05-08 via ABCB NCC 2022). In higher rainfall areas or where surface drainage is less certain, 50 mm per metre (1:20) applies.
  • Slab must sit minimum 50 mm above adjacent paved areas that fall away from the building (NCC 2022 Part 3.3, verified 2026-05-08).
  • Fall to drainage pits or swales: minimum 1:100 for sheet drainage on paving surfaces, steeper where possible to prevent ponding.

3. Sub-grade preparation

The sub-grade is the natural ground beneath everything. It must be:

  • Stripped of topsoil, organic material, vegetation and roots
  • Proof-rolled or tested for soft spots (depressions, fill areas, old services trenches)
  • Soft areas cut out and backfilled with compacted roadbase or lean-mix concrete
  • Compacted to at least 95% Standard Maximum Dry Density (SMDD) for driveways; 90% SMDD for pedestrian areas

Poor sub-grade preparation is the number one cause of paving settlement. Sites with reactive or expansive soils (Class M, H1, H2 or E per AS 2870) need engineering input before paving is laid.

4. Sub-base layer

Per AS 3727.1:2016 (verified 2026-05-08 via Standards Australia):

ApplicationMinimum compacted sub-base depth
Pedestrian only (paths, patios)75 mm
Driveway, vehicles under 3 t GVM100 mm
Driveway, vehicles 3 to 10 t GVM150 mm

Material: crushed rock roadbase (DGB20 or equivalent), well-graded, free of organic material. Compact in maximum 100 mm lifts. Test compaction (plate test or nuclear density gauge) before laying bedding sand. A single pass of a plate compactor is rarely enough.

5. Bedding sand (segmental pavers only)

For segmental pavers (concrete or clay/brick):

  • Sand type: Coarse washed concrete sand (not fine beach sand, not brickies sand). Fine sands migrate under pavers and cause differential settlement.
  • Depth: 30 mm uncompacted, which compacts to approximately 25 mm under the paver. Do not exceed 30 mm: thicker beds are unstable and cause rocking. Per AS 3727.1:2016 (verified 2026-05-08).
  • Screed: Level the sand to consistent height using screed rails, then remove rails and infill. Do not walk on screeded sand before paving.
  • Bedding sand is not glue: It provides uniform bearing support, not adhesion. Edge restraints carry the lateral load.

For poured concrete: no bedding sand. Concrete is poured over sub-base direct with SL72 or SL82 mesh reinforcement per AS 3600.

6. Edge restraints

Edge restraints prevent paver migration and bedding sand loss at the perimeter of any segmental paving area. Required at all free edges, including:

  • Perimeter of driveways, paths and patios not abutting a kerb, wall or concrete edge beam
  • Any change of paving material or direction
  • Expansion joints every 6 m to 8 m in runs exposed to direct sunlight or temperature variation

Types: steel or aluminium edge restraint systems, concrete haunching (minimum 50 mm wide, 100 mm deep), or existing concrete/masonry structures. Plastic snap-in edge restraints are adequate for pedestrian-only paving; driveways need concrete haunching or heavy-duty metal restraint.

Secure restraints at maximum 600 mm centres on any flexible-set paving system (verified from AS 3727.1:2016 scope, CMAA PA01 guidance).

7. Paver laying

Pattern: Herringbone (45-degree or 90-degree) is the highest-interlocking pattern for driveways; basketweave and running bond are adequate for pedestrian areas. For driveways, herringbone is recommended by CMAA to resist vehicle braking forces.

Paver specifications:

TypeMinimum thicknessTypical use
Concrete segmental paver60 mm (pedestrian), 80 mm (driveway)Paths, patios, driveways
Clay/fired brick paver50 mm (pedestrian), 65 mm (driveway)Paths, patios, driveways
Natural stone (granite, travertine, limestone)20 mm to 30 mm (pedestrian only)Patios, pool surrounds
Concrete slab (cast in situ)75 mm (pedestrian), 100 mm (light vehicle)Driveways, hardstands

Brisbane City Council requires minimum 40 mm paver thickness for driveways as part of their crossover technical standard (verified 2026-05-08 via Brisbane City Council). Other councils vary.

Joints: 2 mm to 5 mm joint width for concrete segmental pavers. Fill with fine kiln-dried sand after laying; compact pavers with a plate compactor fitted with a rubber pad. Recheck levels after first compaction pass.

8. Drainage connections

  • Surface water from paved areas must discharge to a lawful point: kerb and gutter, stormwater drainage easement, or absorption trench (where soil and council permit it). Do not direct runoff onto neighbouring properties.
  • AS/NZS 3500.3:2025 governs stormwater drainage systems. Work on the stormwater drainage system (beyond surface grading) is licensed plumbing work in all states (verified 2026-05-08 via VBA).
  • Slot drains and grated pits within paved areas must be designed to handle the design rainfall intensity for the site. Check council DCP or a hydraulic engineer for larger impervious areas.

Tolerances and acceptance

Per current HIA Guide to Materials and Workmanship and relevant state Guides to Standards and Tolerances. Verified numerical values pending HIA member access.

DefectIndicative toleranceNotes
Surface regularity (paved areas)[HIA-064]Typically assessed under a 3 m straightedge
Individual paver level difference (lipping)[HIA-065]Lipping between adjacent pavers is a trip hazard
Cross-fall deviation from design[HIA-066]Critical where falls drain to pits or away from structures
Joint width variation2 mm to 5 mm for concrete segmental paversAS 3727.1:2016 guidance

Documents needed

  • Council crossover/driveway permit application (verge section)
  • Site drainage plan (show falls, pits, legal point of discharge)
  • Sub-base compaction test results (plate test or NDG) for driveways
  • Paver product data sheet (confirming thickness and application class)
  • Plumber/drainer licence details if stormwater work involved

Common holds

IssueRisk
Crossover permit not lodged before startCouncil stop-work; reinstatement at your cost
Sub-grade not compacted or testedSettlement within 6 to 12 months; paver pop-out and lipping
Bedding sand too thick (over 30 mm)Paver rocking, uneven surface, joint failure
Insufficient fall away from buildingWater ingress under slab edge; NCC 2022 Part 3.3 non-compliance
No edge restraints at free perimeterPaver creep, bedding sand washout, trip hazards
Sand in joints not swept and compactedJoint failure, weed growth, sand migration
Stormwater not connected to lawful pointCouncil enforcement; neighbour dispute
Overland flow path blockedFlooding liability; council enforcement

References

See also


Last updated: 2026-05-08. Verified: 2026-05-08. Quarterly review for currency.