glossary Glossary 5 min read

SOPA (Security of Payment Act)

SOPA is the family of state Security of Payment Acts: fast-track adjudication for unpaid construction progress claims. NSW 1999; QLD BIF; VIC 2002; WA 2004.

Ask Chalkline about this →

SOPA is the industry shorthand for the Security of Payment Acts that exist in every Australian state and territory, providing contractors and subcontractors a fast-track statutory pathway to enforce unpaid progress claims. Each state has its own version with subtle differences in timing, claim form, reference dates, and adjudicator panels, but they share a common philosophy: pay now, argue later: adjudicators make interim binding cashflow decisions in 8-12 weeks, and either party can litigate the underlying dispute separately. Verified per current state legislation (2026-05-16).

State-by-state SOPA legislation:

JurisdictionActStyle
NSWBuilding and Construction Industry Security of Payment Act 1999East Coast
VICBuilding and Construction Industry Security of Payment Act 2002East Coast
QLDBuilding Industry Fairness (Security of Payment) Act 2017 (BIF Act)East Coast, trust-mechanism enhanced
SABuilding and Construction Industry Security of Payment Act 2009East Coast
TASBuilding and Construction Industry Security of Payment Act 2009East Coast
ACTBuilding and Construction Industry (Security of Payment) Act 2009East Coast
WAConstruction Contracts Act 2004West Coast
NTConstruction Contracts (Security of Payments) Act 2004West Coast

East Coast vs West Coast SOPA models:

FeatureEast Coast (NSW, VIC, QLD, etc.)West Coast (WA, NT)
TriggerPayment claim served by claimantDispute notice + payment dispute
Respondent’s mandatory schedulePayment schedule must be issued within 10-14 days (or deemed admission)No mandatory schedule; respondent’s silence less consequential
Adjudicator’s scopeStrictly the payment claim and any payment schedule reasonsBroader; may consider any payment dispute
Default positionIf no payment schedule: claimant wins by defaultDefault rules less harsh; less risky for respondent to ignore claim
Used byMost subbies in eastern statesLess commonly used in WA/NT than expected

The standard SOPA cashflow:

1. Subbie does work → Payment claim issued

2. Head contractor responds: Payment schedule (or deemed admission if silent within 10-14 days)

3. If unpaid: Adjudication application within 10 BD typical

4. Adjudicator's determination within 10 BD of response

5. Pay or have judgment debt registered (s.25 cert in NSW)

6. Garnishee, writ, charging order, statutory demand if unpaid

Total elapsed time: 8-12 weeks to enforceable judgment.

Critical SOPA timings (NSW):

ActionTime limit
Payment claimIssued at any reference date (typically end of month); progress on a project
Payment schedule10 business days after receiving payment claim (or as contract specifies, whichever shorter)
Adjudication applicationWithin 10 BD of payment schedule (or due-but-not-served date)
Adjudicator acceptanceAround 4 BD
Adjudication response (respondent)Later of: 5 BD after application, OR 2 BD after acceptance
DeterminationWithin 10 BD of response
Payment of adjudicated amountWithin 5 BD of determination
Certificate registration in courtAt any time after payment date passes

Who is covered by SOPA:

PartyCovered under SOPA?
Subbie (commercial relationship)Yes; primary beneficiary
Subbie’s subbie (sub-subbie)Yes
Head contractor against principalYes
Owner-builder against engaged builderNSW: NO (HBA pathway instead); other states: varies
Owner against builder (residential)NSW: NO since 2014; QLD: NO; VIC: limited
Cleaner, security guard, etc.Yes, if construction-related

In NSW the owner-occupier exclusion (since 2014) was tightened in 2024 to exclude unlicensed subbies entirely from SOPA, requiring NSW Fair Trading or contract pathways instead.

Cross-state notable points:

StateNotable feature
NSWOwner-occupier excluded from SOPA; subbie must use HBA path; unlicensed subbies excluded since 20 Aug 2024
QLDBIF Act adds Project Trust for projects over $1M private / $10M public; trust funds protect subbie payments
VIC”Excluded amounts” restriction repealed effective 15 April 2026; previously excluded set-offs, damages, etc. from adjudication
WAWest Coast model; less aggressive default; less commonly used
NTWest Coast model

Builder takeaway:

  • Treat every payment claim as serious; lodge a payment schedule within the SOPA window every time.
  • If you’ve defaulted on a payment schedule, expect a deemed admission and an adjudication application landing fast.
  • Document the project scope, variations, and deductions in real time; you have only the payment schedule reasons to rely on later.
  • For project trusts (QLD) on large jobs, maintain the trust account discipline; non-compliance is a regulator offence.
  • Brief the office staff on SOPA timings; missing a 10 BD deadline is the #1 SOPA defect.

Also known as: Security of Payment Act; SoPA; BIF Act (QLD); Construction Contracts Act (WA, NT).

Category: Contracts & commercial.

See also


Last updated: 2026-05-16. Verified: 2026-05-16. Quarterly review for currency.