Payment claim (Security of Payment Act)
A payment claim is the statutory form of invoice under each state's Security of Payment Act. Specific content rules apply, distinct from a generic invoice.
Ask Chalkline about this →A payment claim is the statutory form of progress claim served under each state’s Security of Payment Act (SOPA). Each Act allows a contractor or subcontractor who has done work to issue a payment claim, then forces the receiving party to either pay it in full or serve a payment schedule explaining what they will pay and why. A payment claim is not a generic invoice; it is a statutory document that unlocks the SOPA enforcement pathway (adjudication, debt recovery, suspension of work).
Content requirements (state-specific):
| State | Key rules |
|---|---|
| NSW (SOPA 1999) | Must identify the work, claim an amount, state that it is made under the Act, be served on a reference date. |
| Vic (SOPA 2002) | Similar to NSW; must identify work and amount, state the Act, serve on reference date. |
| Qld (BIFA 2017) | Embedded in the Building Industry Fairness Act; “supporting statement” disclosure required for head contractor claims. |
| WA (SOPA 2021) | New regime modelled on east-coast Acts; trust account rules layered on. |
| SA (BCISPA 2009) | Mirrors NSW model. |
Common builder errors:
- Calling a regular invoice “a payment claim” without meeting the statutory content rules: loses the SOPA enforcement leverage.
- Issuing multiple claims for the same reference date: only one valid claim per reference date in most jurisdictions.
- Failing to identify the work claimed: claim can be challenged as defective.
- Wrong delivery method: each Act prescribes service rules (email, post, hand delivery); a non-compliant service date can void the timetable.
What follows a payment claim:
- Recipient has a strict response window (typically 10-15 business days, state-specific) to serve a payment schedule.
- No payment schedule + no payment: claimant can recover the claimed amount as a statutory debt OR proceed to adjudication.
- Payment schedule served: dispute over the scheduled amount goes to adjudication.
For builders:
- Use SOPA-compliant payment claim templates for all progress claims. The leverage of a statutory claim over a generic invoice is significant.
- Track reference dates in the contract. Each contract has a reference date pattern (monthly, fortnightly, on milestone). Claims must align.
- Diary the response window the day you issue a claim. If no payment schedule lands by the deadline, the recovery pathway is immediate.
Also known as: SOPA payment claim, progress claim under SOP Act, statutory payment claim.
Category: Contracts / payments / SOPA.