Klip-Lok roofing profile

Klip-Lok is Lysaght's concealed-clip standing-seam steel roofing profile: 41 mm rib, 1 degree minimum pitch, the premium low-pitch contemporary choice.

Ask Chalkline about this →

Klip-Lok is Lysaght’s concealed-clip standing-seam steel roofing profile, designed for low-pitch and contemporary architectural roofs where no visible fastener heads are wanted on the finished surface. The sheet has a vertical rib that clips over a concealed plastic or steel clip screwed to the support; the next sheet snaps over the same clip. No screws penetrate the upper surface of the pan.

Variants

ProfileRib heightCover widthMinimum pitch
Klip-Lok 40641 mm406 mm1 degree (1 in 50)
Klip-Lok Classic 700~41 mm (fluted pan)700 mm1 degree at 0.48 BMT, 2 degrees at 0.42 BMT

Klip-Lok Classic 700 has longitudinal fluting along the pan that improves stiffness on the wider cover width. Verified 2026-05-16 from Lysaght Klip-Lok 406 brochure and Lysaght professionals product page.

When it’s used

  • Low-pitch roofs below 5 degrees where pierce-fix profiles (Trimdek, Custom Orb) need to be steepened to maintain weather resistance.
  • Contemporary architectural designs where the standing-seam look is the design intent.
  • Long sheet runs where pierce-fix penetration count would create high failure risk.
  • Wall cladding for a clean concealed-fix aesthetic.

Trade-offs vs pierce-fix profiles

DriverKlip-Lok advantagePierce-fix advantage
Sheet costMore expensive (15-25% premium typical)Cheaper per m²
Install timeSlower (clip placement)Faster (direct screw)
Penetration countNone on panOne every batten
Low-pitch capability1 degree2-5 degrees typical
Aesthetic (contemporary)CleanerVisible fasteners

On-site checks

  • Clips correctly aligned with stud or purlin centres before fitting.
  • Sheet pan free of foot traffic damage; light walking only on the rib, never on the pan.
  • Underside of overlaps free of swarf; metal shavings between pan and clip will corrode.
  • Compatible flashing details (Lysaght or matched colour/material) for ridges, valleys, and side laps.

Also known as: KLIP-LOK, Lysaght Klip-Lok, Klip-Lok 406, Klip-Lok Classic 700.