Fixing stage
Fixing stage is the construction and progress-claim stage after lock-up, when internal linings, architraves, skirtings, doors and cabinets are fixed, before completion.
Ask Chalkline about this →The fixing stage is the construction (and progress-claim) stage after lock-up, when the internal linings, architraves, skirtings, doors, built-in cabinets, and baths and basins are fixed in place. It is the step between lock-up and practical completion in the standard HIA/MBA stage sequence.
Fixed-price residential contracts are usually paid in stages, each tied to an observable point in the build. The common sequence is:
- Deposit
- Base (slab/footings down)
- Frame (frame up and approved)
- Lock-up (roof on, external walls and windows/doors in, the building can be locked)
- Fixing (internal fit-out fixed: linings, trims, doors, cabinetry, fixtures)
- Completion (practical completion, final payment)
“Fixing” is the trade term for fastening the internal joinery and fittings in place, so the fixing stage covers second-fix carpentry, internal doors, skirting and architrave, built-in robes and kitchen cabinetry, and the fixing-off of plumbing and electrical fixtures. The percentage of the contract price attached to it is set in the contract’s progress-payment schedule.
For a builder the practical points are to claim the fixing-stage progress payment only when the stage is genuinely reached (claiming ahead of the work is a common dispute and, for owner-protection, the law limits front-loading), and to align the claim with the contract’s stage definition rather than your own read of “mostly done.” For an owner, the fixing-stage claim is the cue to inspect the fit-out quality before paying, because once you are at fixing the next stop is completion and final money.
Also known as: Fixing (stage), fit-out stage.
Category: Contracts / Progress payments.
Related
See also
References
- Progress claims (Chalkline) (verified 2026-06-02)
Last updated: 2026-06-02. Verified: 2026-06-02. Quarterly review for currency.