Architect-administered contract
An architect-administered contract is one where the architect administers the contract: certifying payments, variations and EOTs as an impartial third party.
Ask Chalkline about this →An architect-administered contract is a building contract where the architect acts as the contract administrator (on commercial contracts, the superintendent): the party who administers the contract between owner and builder during construction.
What the architect does in this role:
- Issues instructions and answers the builder’s requests for information.
- Assesses and certifies progress claims, deciding what the builder is paid each month.
- Assesses variations and extension-of-time claims.
- Inspects the works at key stages and at practical completion.
- Acts as first-line decision-maker on disputes about the works, and is meant to act impartially between owner and builder even though the owner pays them.
Where it’s used: common on architect-designed homes and on commercial contracts (for example AS 4000 / AS 4902, where the role is called the superintendent). Less common on volume or project-home builds, which are usually administered by the builder under a domestic contract.
Why it matters to a builder:
- A third party, not the owner, decides your progress payments, variations, and EOTs. Get your claims and notices in correctly and on time: the administrator assesses them against the contract, not on goodwill.
- The architect wears two hats, the owner’s designer and the (supposedly impartial) contract administrator. Watch for design problems being administered as “builder’s defects”.
- Know the contract: how claims are submitted, the assessment timeframes, and how to dispute a certificate you disagree with.
Also known as: superintendent-administered contract; architect as contract administrator.