Heritage Act 1977 (NSW)
NSW Heritage Act 1977 establishes the State Heritage Register, Heritage Council of NSW, and Section 60 works approval regime. Turns SHR sites into concurrence DAs.
Ask Chalkline about this →TL;DR
The Heritage Act 1977 (NSW) establishes the State Heritage Register (SHR), the Heritage Council of NSW, and the Section 60 works approval regime. Any work on or affecting an SHR-listed place requires a Section 60 approval from the Heritage Council. Section 146 imposes a duty to notify the Heritage Council on discovery of an unmapped “relic” (typically pre-1900 archaeology). Practically, the Act turns every SHR-listed property into a concurrence-style DA: council assesses the planning permit AND Heritage NSW concurs on the Section 60. Builders in NSW heritage country need both pathways managed in parallel.
Scope
The Heritage Act 1977 governs:
| Object | What the Act does |
|---|---|
| State Heritage Register (SHR) | State register of places of state heritage significance |
| Heritage Council of NSW | Peak NSW heritage advisory body |
| Section 60 approval | The works approval required for any work affecting an SHR place |
| Interim Heritage Order (IHO) | Time-limited protection while an item is being assessed |
| Section 146 relic notification | Duty to report discovery of an unmapped relic |
| State Heritage Inventory | Broader database including SHR and council-listed items |
The Act does NOT cover items listed only on a council’s LEP Heritage Schedule; those are governed by the planning permit regime under the Environmental Planning and Assessment Act 1979.
SHR vs council heritage listing
NSW has two heritage layers builders need to distinguish:
| Layer | Authority | Approval required |
|---|---|---|
| State Heritage Register (SHR) | Heritage Council of NSW | Section 60 approval + DA / CDC |
| Council LEP Heritage Schedule | Council | DA only (no Section 60) |
| Heritage Conservation Area (HCA) | Council | DA only (no Section 60) |
Most heritage-listed properties in NSW are LEP-only, not SHR. SHR is the higher tier; SHR places are typically nationally significant (e.g. the Queen Victoria Building, the Sydney Opera House precinct, historic homesteads). Always check both layers.
The Section 60 approval regime
For an SHR-listed place, work requires a Section 60 approval from the Heritage Council:
- Any alterations or additions to fabric.
- Demolition (full or partial).
- Excavation in the curtilage.
- Sub-division of the lot.
- Change of use affecting heritage values.
- External painting in some cases.
The Section 60 application includes:
| Document | Source |
|---|---|
| Heritage Impact Statement | Heritage consultant |
| Conservation Management Plan (if exists) | Often pre-existing for major SHR places |
| Drawings | Architect |
| Photographic record | Heritage consultant |
| Specifications including materials and methods | Architect + heritage consultant |
| Owner’s consent | Lot owner |
Heritage NSW assesses; the Heritage Council determines.
Integrated development and concurrence
For SHR places, the DA and Section 60 typically run as integrated development under EP&A Act Section 4.46. The council is the consent authority for the DA, but Heritage NSW provides concurrence (effectively a binding input). If Heritage NSW won’t concur, the DA cannot be approved.
This means:
- The DA and Section 60 are lodged together (in practice via the Planning Portal).
- The council and Heritage NSW assess in parallel.
- Heritage NSW’s concurrence either grants or refuses; council follows.
Section 146: discovery of a relic
A relic under the Heritage Act 1977 is broadly defined as a deposit, object, or material evidence of land use in NSW, dating from before 1900.
Section 146 imposes a duty:
- Stop work in the affected area.
- Notify the Heritage Council “within a reasonable time”.
- Do not disturb the relic further until the Heritage Council advises.
Penalties for non-compliance are substantial. The relic notification duty applies to everyone on site, including subcontractors. Brief at engagement.
Aboriginal heritage: separate regime
Aboriginal heritage in NSW is governed under the National Parks and Wildlife Act 1974 (Part 6), not the Heritage Act 1977. The two regimes are independent:
- Heritage Act 1977: post-1788 / European-era heritage.
- NPW Act Part 6: Aboriginal heritage (objects and places).
An Aboriginal heritage finding triggers separate stop-work and notification duties under NPW Act Part 6 and AHIMS. If the lot has Aboriginal heritage indicators, engage a specialist Aboriginal heritage consultant.
When the Act applies to a residential build
Most NSW residential builds are NOT SHR-listed. The Heritage Act typically applies in:
| Situation | Heritage Act involvement |
|---|---|
| Lot on the SHR | Full Section 60 regime |
| Lot adjoining an SHR place | May require Heritage NSW concurrence on the DA |
| Lot on council LEP Heritage Schedule only | Planning regime, no Section 60 |
| Excavation discovers pre-1900 deposits | Section 146 stop-work |
| Aboriginal heritage discovery | NPW Act Part 6 stop-work (separate from Heritage Act) |
The Section 10.7 planning certificate discloses both SHR and LEP heritage listings.
Common builder issues
- SHR listing missed at lead: discovered post-design lock-in. Concurrence pathway adds 3-6 months.
- Section 146 relic discovery mid-construction: excavation reveals pre-1900 deposits. Work stops; archaeological consultant engaged; permit conditions follow.
- Subcontractor not briefed on Section 146 / NPW Act obligations: brief at engagement and document.
- Treating LEP-listed and SHR-listed identically: SHR is substantially more rigorous; budget and program accordingly.
Process: Section 60 application
- Pre-application meeting with Heritage NSW (recommended). Free for residential.
- Engage a heritage consultant: prepares the SoHI and conservation strategy.
- Prepare integrated development package: DA + Section 60 together.
- Lodge via NSW Planning Portal as integrated development.
- Public notification by council (typically 14-28 days).
- Concurrence assessment by Heritage NSW, typically 3-6 months.
- Council determination following concurrence.
- Permit (with conditions) issued if approved.
Total timeline for an SHR-listed residential build: 6-12 months from lodgement to construction start. Plan accordingly.
For builders
- Check the SHR at lead (heritage.nsw.gov.au). Free, takes 5 minutes.
- Order the Section 10.7 to confirm SHR + LEP heritage listings.
- Brief every subcontractor on Section 146 and NPW Act stop-work obligations. Document.
- Engage a heritage consultant early for any SHR-listed work.
- Plan for integrated development timeline (6-12 months) on SHR sites.
- Confirm contract works insurance covers heritage-related work before commencement.
References
-
Heritage NSW: https://www.heritage.nsw.gov.au (verified 2026-05-15).
-
State Heritage Register: https://www.hms.heritage.nsw.gov.au (verified 2026-05-15).
-
Heritage Act 1977 (NSW) full text: https://legislation.nsw.gov.au (verified 2026-05-15).
Related
See also
Last updated: 2026-05-15. Verified: 2026-05-15.